Choosing an IT investment

Deciding on a project by its cash flows: schedule, discount rate, net present value, internal rate of return, payback period, return on investment and criteria that cannot be priced.

  • 21 cards
  • 5 topics
  • Free

The outline, topic by topic

Each topic is weighted the way the exam weighs it.

  1. Concepts
  2. Questions
  3. The numbers
  4. The curves
  5. Scenarios

A few cards from the deck

  • Discount rate: what is it?

    Show the answer

    The annual rate used to bring a future flow back to its value today, reflecting the cost of capital and risk.

    A euro received in a year is worth less than a euro today: at 10 %, 40,000 € in a year is worth 40,000 / 1.1 ≈ 36,364 € now.

  • 100,000 € invested, then 40,000 € of gains a year for three years, at 10 %. What is the net present value?

    • −526 €
    • +20 000 €
    • −100 000 €
    • +526 €
    Show the answer

    −526 €

    36,364 + 33,058 + 30,053 = 99,474 € of discounted gains, minus 100,000 €: −526 €. +20,000 € forgets to discount (120,000 − 100,000); the sign is negative despite 120,000 € of gains.

  • A project is accepted when its net present value is … at the chosen discount rate.

    Show the answer

    A project is accepted when its net present value is positive at the chosen discount rate.

    At zero, the project earns exactly the required rate: you are indifferent. Below, investing at the required rate would do better.

  • Net present value: what is it?

    Show the answer

    The sum of a project's flows, gains minus outlays, each brought back to today at the discount rate.

    Positive, it says the project earns more than the required rate; negative, that it destroys value: gains brought back to today do not repay the outlay.