  • Software life cycle: what is it?

    Show the answer

    The sequence of major activities a piece of software goes through, from stating the need to its retirement, via building and maintenance.

    Choosing a life-cycle model means choosing the order of activities and when the client gives feedback, not how good each activity is.

  • In the V-model, which test checks the detailed design, that is each component taken on its own?

    • Unit tests
    • Integration tests, which assemble the components
    • Validation tests of the whole system
    • Acceptance by the client
    Show the answer

    Unit tests

    Each design level has its own test level: detailed design and unit tests, general design and integration tests, specifications and validation tests, need and acceptance.

  • An … redoes and improves what already exists; an … adds one more usable piece to the product.

    Show the answer

    An iteration redoes and improves what already exists; an increment adds one more usable piece to the product.

    They combine: each short cycle adds an increment and improves the previous ones based on feedback.

  • Waterfall model: what is it?

    Show the answer

    A model where the phases follow one another in a single sequence, each finished and validated before the next, with testing coming only after coding; going back is rare and costly.

    It suits a stable, well-known need. Its flaw: the client only sees the product at the end, when a misunderstanding costs the most.

  • The need is vague, the client is available and the market is moving. The team works in waterfall and delivers a stale product after 18 months. Which life cycle should it adopt?

    • A V-model, to write test plans as early as the design
    • Waterfall, with a longer specification phase
    • A V-model, with more frequent design reviews
    • An iterative and incremental cycle, with a usable version at regular intervals
    Show the answer

    An iterative and incremental cycle, with a usable version at regular intervals

    The cause is no client feedback before the end. A longer specification does not make the need more stable; regular versions let the team correct course early.