Gantt chart

The Gantt chart as a calendar view of a schedule: bars, dependencies, earliest or latest placement, visible float, critical path, milestones, progress and load per resource.

  • 26 cards
  • 7 topics
  • Free

The outline, topic by topic

Each topic is weighted the way the exam weighs it.

  1. Concepts
  2. Questions
  3. Sort and link
  4. On the timeline
  5. The numbers
  6. Scenarios
  7. Understand

A few cards from the deck

  • Bar of a Gantt chart: what is it?

    Show the answer

    A rectangle placed on a date axis that represents a task: its position gives the start, its length the duration.

    A task's end is therefore its start plus its length. Two bars that overlap in time run in parallel.

  • On day 12, expected progress = (12 − start) / duration. Which is the only task running late?

    ```text
    Task Start Duration Progress
    T1 0 6 100%
    T2 4 10 30%
    T3 10 6 40%
    T4 12 4 0%
    `

    • T2, at 80% expected, 30% done
    • T3, because it is below 50% complete
    • T4, because it is at 0%
    • T1 and T2, because they began before day 12
    Show the answer

    T2, at 80% expected, 30% done

    T2 should be at (12 − 4) / 10 = 80%. T3 should be at (12 − 10) / 6, i.e. 33%: at 40%, it is ahead. T4 starts on day 12, 0% is normal. T1 is finished, so not late.

  • In a Gantt chart, a bar's … represents the task's duration, and its horizontal position its ….

    Show the answer

    In a Gantt chart, a bar's length represents the task's duration, and its horizontal position its start.

    A bar's thickness has no link with the task's importance: only the horizontal axis carries information.

  • Milestone: what is it?

    Show the answer

    A marker of zero duration, often drawn as a diamond, that flags a key date of the project: delivery, approval, end of a phase.

    A milestone consumes no time or resource. It is used to check progress: on its date, the tasks before it must be finished.