Estimating effort

Effort, duration and deadline, the person-day, the estimation methods (analogy, experts, three points, parametric) and the traps that derail a schedule: Brooks's law, optimism bias.

  • 26 cards
  • 4 topics
  • Free

The outline, topic by topic

Each topic is weighted the way the exam weighs it.

  1. Concepts
  2. Questions
  3. Sort and link
  4. The numbers

A few cards from the deck

  • Effort of a task: what is it?

    Show the answer

    The amount of work needed to complete it, independent of the calendar and of the number of people, expressed in person-days.

    Sixty person-days is sixty days for one person or, if the work splits well, twenty days for three: the effort stays the same, the calendar does not.

  • A project manager writes: “the task is 20 person-days, so it takes 20 days”. What is wrong?

    • It mixes up effort and duration: duration also depends on staffing
    • It forgets that a person-day is counted in calendar hours
    • It forgets that the client sets the effort, not the project team
    • There is no mistake: an effort in person-days is a duration in days
    Show the answer

    It mixes up effort and duration: duration also depends on staffing

    Effort measures work, duration measures elapsed time. Two full-time people would do 20 person-days in 10 days, one half-time person in 40.

  • … leads people to estimate from the best-case scenario; one remedy is to compare past estimates with the … durations.

    Show the answer

    Optimism bias leads people to estimate from the best-case scenario; one remedy is to compare past estimates with the actual durations.

    People usually underestimate their own tasks: the record of past gaps offers a correction based on facts, not on good intentions.

  • Duration of a task: what is it?

    Show the answer

    The calendar time elapsed between its start and its end, which depends on the effort, the staff assigned and their availability.

    An effort of 10 person-days given to one person working half-time lasts 20 working days: the duration is derived from the effort, it is not the same thing.