Backlog and estimation

The product backlog (ordered, refined, detailed at the top), relative estimation in points, planning poker, velocity and delivery forecasting, ordering by value and effort.

  • 24 cards
  • 6 topics
  • Free

The outline, topic by topic

Each topic is weighted the way the exam weighs it.

  1. Concepts
  2. Questions
  3. Sort and link
  4. The numbers
  5. Scenarios
  6. Understand

A few cards from the deck

  • Product backlog: what is it?

    Show the answer

    An ordered list of everything thought necessary to evolve the product, kept up to date at all times.

    It is ordered, not just listed: the top holds what will be done first, the bottom holds still-vague ideas.

  • A team committed to 25 points. At the end of the sprint, items totalling 20 points meet the Definition of Done, and 5 points are 90% complete. What is the velocity of the sprint?

    • 20 points
    • 25 points
    • 24.5 points
    • 22.5 points
    Show the answer

    20 points

    Velocity counts only what is fully finished. The 90% items are worth 0 points for this sprint and are counted in the sprint where they are finished.

  • The values on planning poker cards follow a sequence close to the … sequence, whose gaps grow with size.

    Show the answer

    The values on planning poker cards follow a sequence close to the Fibonacci sequence, whose gaps grow with size.

    The gap between two values grows with size, reflecting that uncertainty grows with it: nobody decides between 12 and 13.

  • Backlog refinement: what is it?

    Show the answer

    An ongoing activity of splitting, detailing, estimating and reordering backlog items so they are ready to enter a sprint.

    The top of the backlog is refined mostly, just before it is needed: detailing the bottom would be wasted work, as priorities will change.