A project's budget

Costing a project: daily rate, budget lines, capital and running expenses, contingency, total cost of ownership, and tracking with budget, committed, actual and remaining spend.

  • 27 cards
  • 5 topics
  • Free

The outline, topic by topic

Each topic is weighted the way the exam weighs it.

  1. Concepts
  2. Questions
  3. Sort and link
  4. The numbers
  5. Scenarios

A few cards from the deck

  • Daily rate: what is it?

    Show the answer

    The full cost of one person's working day, which includes social charges and a share of overheads, not just the gross salary.

    Effort multiplied by this rate gives the staff cost: 45 person-days at €400 a day make €18,000. Using the gross salary underestimates the budget.

  • A developer earns €3,000 gross a month. Why is costing his day at 3,000 / 20 = €150 in a budget a mistake?

    • A day also costs social charges and overheads
    • You must divide by 30 calendar days, which gives €100 a day
    • Gross salary never enters a project's cost
    • A budget is costed in hours, never in days
    Show the answer

    A day also costs social charges and overheads

    For the company, a day costs far more than the gross salary: employer charges, workstation, management, non-billable days. The budget must reflect that full cost.

  • A staff work package's budget is the effort in person-days multiplied by the …, plus the ….

    Show the answer

    A staff work package's budget is the effort in person-days multiplied by the daily rate, plus the contingency reserve.

    45 person-days × €400 = €18,000, then + 10 % contingency: €19,800.

  • Contingency reserve: what is it?

    Show the answer

    A sum set aside in the budget, often as a percentage of the total, to absorb unforeseen events and any risks that materialise.

    It is managed as a whole and in plain sight, at project level: it is neither hidden inside each task nor spent without the project manager's decision.